Screen Reader Access Skip to Main Content Font Size   Increase Font size Normal Font Decrease Font size
Indian Railway main logo
Search :
Find us on Facebook   Find us on Twitter View Content in Hindi
National Emblem of India

About Us

Divisions

News & Updates

Tenders

Supplier Information

Passenger information

Contact Us

Divisions
   SEALDAH
      Departments
         Electrical /Genl


Goto Yahoo!!


 
Bookmark Mail this page Print this page
QUICK LINKS
Electrical /Genl



 WELCOME

Electrical General Department

Eastern Railway, Sealdah



Organization Chart


Jurisdiction of Power wing

SDAH-I

SDAH-II

SPR

BT

NH

CP

RHA

SDAH- Budge-Budge

DRM bulding officer colony,    B.R .Singh Hospital

Ballygunge-Sonarpur

Bisharpara-Barasat

Belgharia- Kalyani

Kolkata Terminal-Princep Ghat

Madanpur-Ranaghat

SDAH-Birati

NAP
JJC
BLVD
GM Bunglow GHPR

Sonarpur-Canning

Barasat-Petrapol

Ranaghat-Gede

SDAH-Majerhat

Burn standard, Behala Stadium

Sonarpur-Diamond Harbar

Barasat-Hasnabad

Ranaghat-Lalgola

Baripur-Namkhana

Assets of Electrical (Power wing)

Power Supply installation

WBSEDCL Supply points (HT)

21 nos

CESC supply points (HT)

24 nos

WBSEDCL Supply points (LT)

420 nos

CESC supply points (LT)

87 nos

Standby DG Sets

25 nos

Total no. of stations

205 Nos

Electrified stations

205 Nos

Non-Electrified station

NIL

Other Asset

Lifts

46 nos

Escalator

22 nos

Major Building/Complex

6 nos

Electrified LC Gate

414 nos

Non-Electrified LC Gate

nil

Central AC plant

71 nos

AC package Unit

16 nos

Window AC unit

380 nos

Split AC unit

576 nos

Tower AC

6 nos

Non-traction Energy Consumption & Bill pattern


Year

Consumption (MU)

Bill (Rs in Crore)

2015-16

50.54

44.18

2016-17

48.26

40.67

2017-18

45.95

39.39

2018-19

42.35

37.16

2019-20

41.58

36.55

2020-21

33.25

29.64

2021-22

36.38

31.95

2022-23

40.27

35.22

2023-24 ( up to May’23)

7.6

6.45

*Due to Covid Pandemic Non traction energy consumption of FY 2020-21 is very less compared to other years.

Savings in FY 2021-22 compared to 2019-20: 12.5%
Savings in FY 2022-23 compared to 2019-20: 9.5%

Solar Plants in Sealdah Division :

Location

Capacity

D.O.I

NKG RPF Barrack (PPP)

31.68 kwp

31.07.18

KOAA Terminal

(PPP)

468:66 kwp

10.04.19

NH Station

120kwp

23.10.19

LKPR Running Room

10 kWp

February, 2022

NMKA Running Room

10 kWp

February,

2022

SDAH (Non-PPP)

50 kWp

31.03.22

SPR Carshed

05kWp

February, 2022

Kakdwip

05kWp

February, 2022

DDJ Running room

05kWp

Dec’22

Total                                       705 kWp














ACHIEVEMENTS 23-24(up to Aug'23)

ENERGY SAVINGS (NON TRACTION) :

Electrical General Department, Sealdah has increased Non-traction Energy Consumption by only 12.07% in comparison to 21-22 (up to May) irrespective of connected load increase on 17%.   

       Savings In Fuel: Fuel Savings by this department achieved is 4190 kL (Rs. 45 Cr. Appx.) through HOG operation during service and CSS operation during maintenance. as calculated upto May-2023

  Solar Generation and Savings:Electrical General Department has achieved saving of Rs.16,25,600/- approximately as calculated upto July-2023

Domestic Load Segregation: has been done from industrial load introducing new HT supply connection of 250 kW from CESC.

   Way Leave Charges.: Earned Rs.1,94,11,473/- upto July-2023 from different DISCOMs for track crossing.

Capacitor Bank at Majherhat:Successfully commissioned one new 175 KVAR capacitor bank at Majherhat Substation  enabling savings Rs 60000/- per year as anticipated.

Implementation of Smart  and Prepaid Metering System.-Smart Meter -249 numbers have been fitted at Moghal Bagan and Narkeldanga Railway Colonies, Sealdah and 33 numbers prepaid meters have been fitted for vendors upto Decmber-2022.

Implementation of Motion sensors in Platforms: Electrical General Department, Sealdah has successfully implemented motion sensor  system for plat form light and fans at Kolkata Station PF#1 and Gede Station PF#1. Its anticipated cost savings will be  Rs.3.0 lakh per year.

Implementation of Web Based monitoring system of Escalator: Web based monitoring system for 2 nos escalators at Naihati station and 2nos at Ranaghat station has been implemented as the first step towards complete automated monitoring of all lifts/escalators in the division.

Development of Power Supply System:

AT Barasat: Two (02) numbers Transformers of capacity 500 kVA each, 11 kV/415 V Dry Type (Make: Voltamp) commissioned for Coach Washing Plant Work

At Barrackpore: Transformer of 250 kVA capacity, 11kV/415V -01 no (Make: M/s Eastern Transformer) commissioned at Barrackpore Substatin.

Electrical Safety Audit:New Koilaghat Building (G+13) has been audited against its Electrical Safety aspect by Acredited Agency.

Development of Solar Plant with Monitoring System at Naihati:

Solar generation of 120 kWp Plant in Naihati Station has been provided with web based   monitoring system enabling close vigil on its generation data day to day.

Electrical Work at Dumdum Running Room:

It has been provided with electrical items/equipments of power savings like Master Switches, LED lights, BLDC Fans, Solar Geysers, Solar generation Plant as a leap to meet the goal of ‘Green Initiatives’ towards making it ‘GreenBuilding’.

Renovation of RPF Barrack, Dumdum:

Renovation work of RPF Barrack Dumdum has been successfully done by providing every possible energy efficient electrical equipments like- BLDC Fans, Integrated Light LED Fittings, Surface wall mounted indoor LED Lights etc.

Provision of Pump at DRM Building for Monsoon

Two (02) number Dewatering Pumps (each15 HP-Make-Kirloskar) have been installed at DRM building Compound (DDJ End) in view of coping up with consequences of upcoming monsoon season.

New Substation:

One New Sub-stn. 6KV/415V has been installed at Narkeldanga Carshed with new CESC intake point with Contract Demand (CD ) of 220 KW  comprising Equipments: HT VCB – 5 nos. (800A), LT panel 02 nos., Transformer 500 KVA 02 nos., APFC panel 150 KVAR – 01 no.