1. | Maximum Permissible speed between GGLE-TYAE (GGLE-SALE DN Line and SALE-TYAE Up Line) increased from 80KMPH to 90KMPH (Sectional Speed) in Aug, 2020. |
2. | 2 Nos. defective layouts (PT No. 41A & B at JOX) have been corrected by shifting of point Manually in Aug, 2020. |
3. | Chequred plate of BR No. 100 in BDC-SKG section and BR No. 20 in BDC-KWAE section in existing UP and Down Line replaced in Aug, 2020. |
4. | 04 set Points & Xing has been converted from 52 Kg to 60 kg (Under AEN/BHP) in Aug, 2020. Thus cumulative progress 08 nos. |
5. | 01 set Points & Xing has been changed at MYM Under AEN/BDC in Aug, 2020. |
6. | 01 set Points & Xing has been converted to Fan shaped layout from wooden layout at RR Line EMU CS (Under AEN/TR/HWH) in Aug, 2020.. |
7. | 1 set. TTR (only Switch) have been done in Aug, 2020.. Thus cumulative progress is 11 nos. |
8. | 05 nos. TTR (Only xing) have been done in Aug, 2020.. Thus cumulative progress is 42nos. |
9. | 23nos SEJ (23 set 60 Kg) (Improved) replaced/renewed in Aug, 2020.. Thus cumulative progress is 62 nos. |
10. | 7.552Km track renewal (CTR Unit)( TRR(P)-8.720 KM, TSR(P)-5.709 TRR(S)-0.675, TSR(S)-0) done in Aug, 2020. Thus cumulative progress is 17.255 Km. |
11. | 655 nos. Of Thermit Welding done in Aug, 2020. Thus cumulative progress is 3133 nos. |
12. | Scrap of 918.4 MT has been offered in Aug, 2020 from which 918.4 MT has been offered through “as it is where basis”. Thus the cumulative progress is 1205 MT. |
13. | 45.132 km greasing of ERC have been done in Aug, 2020.. Thus cumulative progress is 106.423 Km. |
14. | 662 nos. Joggle Fish Plate fixed over old welds in Aug, 2020. Thus cumulative progress is 2498 nos. |
15. | 1.87 km rail painting have been done in Aug, 2020. Thus cumulative progress is 52.002 Km. |
16. | 100 nos. Glued joints (60kg) & 23 nos Glued joint (52 Kg) have been replaced in Aug, 2020. Thus cumulative progress is 327 nos.( 60 Kg) & 59 nos (52 Kg). |
17. | 250.28 Km Plain Track tamping done in Aug, 2020. Thus cumulative progress is 1052.15 Km. |
18. | 108 sets Turnout tamping done by UNIMAT in Aug, 2020. Thus cumulative progress is 440 nos. |
19. | 26.25 track Km dressing boxing done by BRM in Aug, 2020. Thus cumulative progress is 246.67 Km.
|
20. | 4.855 TKM TSR(P) has been done by PQRS in Aug, 2020.
|
21. | 122.4 TKM rail grinding progress has been done by RGM in Aug, 2020. Thus the cumulative progress is 348 TKM.
|
22. | 7 Km OMS done by Divisional OMS team in Aug, 2020 and no peak has arisen. Thus cumulative progress is 10973 Km. |
23. | Total 20.424 km deep screening (15.56 km by Machine& 4.864 km by manually) in addition of 9 nos. Turn outs (Manual) have been done in Aug, 2020. Thus cumulative progress is 61.459 km and 35 nos T/O. |
24. | 6.370 Thou M3 Ballasting have been done in Aug, 2020. Thus cumulative progress is 42.830 Thou M3. |
25. | 18 nos. Switch and 26 Nos crossing reconditioned in Aug, 2020. Thus cumulative progress is 146 nos. Switches & 57 nos Crossing . |
26. | 110 nos. Weld collar painting done in Aug, 2020. Thus cumulative progress is 635 Nos. |
27. | 56 Nos quarter improved (Type(II)-53 Nos.(AEN/DKAE, AEN/RPH, AEN/BDC, AEN/KWAE, AEN/LLH, AEN/NDAE, AEN/AZ), Type(III)-2 Nos.(AEN/TR/HWH) & Type(V)-1 Nos.(AEN/TR/HWH)) in Aug, 2020. Thus cumulative progress is 101 Nos. |
28. | 34 Nos. Doors & 33 Nos windows have been replaced in Aug, 2020. Thus cumulative progress is 123 Nos Door & 82 Nos windows. |
29. | 1069 M2 road construction (AEN/DKAE & LLH) have been done in Aug, 2020. Thus cumulative progress is 11159 Thou M2. |
30. | 735M boundary wall (630m track, 105m colony) constructed under AEN/NDAE, AEN/BHP, AEN/RPH, AEN/TR/HWH & AEN/LLH in Aug, 2020. Thus cumulative progress is 2481M. |
31. | 303 meter pipeline (AEN/BHP, AEN/DKAE, AEN/LLH) has been replaced in Aug, 2020. Thus cumulative progress is 1722 meter. |
32. | 25 Nos tap connection have been done in Aug, 2020. Thus cumulative progress is 57 Nos. |
33. | 4 Nos Deep tubewell constructed at DKAE in Aug, 2020. Thus cumulative progress is 4 nos. |
34. | 6 Nos PF shed constructed (RPH, KMAE) in Aug, 2020. Thus cumulative progress is 14 nos. |
35. | 1438 M2 PF shed has been improved at BOI, HWH, KLNT Station in Aug, 2020. Thus the cumulative progress is 1938 M2. |
36. | PF benches (capacity 100 Users) constructed (BWN, KMAE Stn) in Aug, 2020. Thus cumulative progress 115 nos(users). |
37. | 128 meter drain has been constructed (under AEN/BDC, DKAE, LLH & BHP) in Aug, 2020. Thus cumulative progress is 569 meter.
|
38. | 341.75 Km USFD testing (Rail 198.48 Km +P& C 94 Km+ Weld 49.27 Km) done in the route where goods & special trains are running in Aug, 2020. Thus cumulative progress is 1743.06 Km. |
39. | Super checking of USFD work have been done by AEN/BHP & BWN in Aug, 2020. |
40. | 13.592KM TFR have been done in Aug, 2020. Thus cumulative progress is 18.821 Km |
41. | 1825 Nos. Trees have been planted (at SAME, BDC, DKAE, AZ & BWN) in Aug, 2020. |
42. | 2 Nos.(800 m2) PF are improved at GPAE and BGAE in Aug, 2020. |
43. | 8 Nos. Toilets (at KJU, BGRA, GPAE, KWAE, BWN, KHN) are improved in Aug, 2020. |
44. | 1 Waiting Hall (At KWAE) and 3 Retiring Room (At BWN) are improved in Aug, 2020. |
|
|
B. | The Gang has performed the following work |
1. | 551 nos. Glued joint attention work done during this month. Thus cumulative progress 2968 nos. |
2. | 294 sets. P & C attention work done during this month. Thus cumulative progress 1235stes. |
3. | 31 nos. Bridge approach attention work done in Aug, 2020.. Thus cumulative progress is 192 nos. |
4. | 28 nos. LC approach attention work done in Aug, 2020. Thus cumulative progress is 360 nos. |
5. | 173 nos. SEJ attended to maintain LWR done in Aug, 2020. Thus cumulative progress is 747 nos. |
6. | 1.464 TKM shallow screening has been done at CDAE Down Loop1 & 2 and GRAE Down Loop in Aug, 2020. Thus the cumulative progress is 2.034 TKM. |
7. | No Rail or Weld Failure occurred in Aug, 2020. |
8. | 918.4 MT scrap disposed in Aug, 2020. |
9. | Renovation of RPF Line BARRACK is done in Tindal Bagan Howrah. |
10. | 0.750 TKM Formation Treatment has been done in Aug, 2020. Thus cumulative progress is 1.250 TKM.
|
C. | Bridge
|
|
1. | Bridge Work done (under PB/LB/Rev.) (1) Br. No. 164 (RUB), Span 2x5x8ft. at km. 106/9-10 in betn. Stn. SDLE-NHT in SBG Loop for the work of Provision of standard height gauge has been completed. (2) Br. No. 231 (RUB), Span 2x1x8.3 ft at Km. 269.02 in betn. Stn. NGF - PKR in SBG for the work of Provision of standard height gauge work has been completed. (3) Br. No. 42 Span 3x (6x13 ft. + 1 x66 ft.) at Km. 22.70 in betn. Stn. SHE- BBAE HWH-BWN M/Line for the work of provision of side pathway work has been completed. |
|
2. | Bridge Inspection:- (1) Benaras ROB, Span 2 x(1x110 ft. + 2 x 30 ft.) in betn. Stn. HWH-LLH in HWH-BWN M/Line. (2) Br. No. 210 (UP & DN), Span 2x (3x40 ft. + 1x60ft.) in betn. Stn. MRR-BSBR in SBG Loop.
|
|
3. | Cleaning & lubricating of bearing of girder:-
(1) Br. No. 56 (DN) Span 32 x 15.25 mtr. at Km. 153.78 in betn. Stn. BDH- BHP in SBG Loop. (2) Br. No. 12 (ROB) Span- 1 x 10 Mtr. at Km. 133.41 in betn. Stn. BPS-NRX in SBG Loop. (3) Br. No. 70 (ROB) Span- 1 x 21.02 Mtr. at Km.159.67 in betn. Stn. BHP-PNE in SBG Loop. (4) Br. No. 93 (ROB) Span- 1 x 21.02 Mtr. at Km.177.29 in betn. Stn. KPLE-ADP in SBG Loop. (5) Br. No. 125 (UP) Span- 2x60 ft. + 1x40 ft. at Km.192.63 in betn. Stn. SNT- GHLE in SBG Loop. (6) Br. No. 125 (Rev.) Span- 3x60ft. at Km. 192.54 in betn. Stn. SNT- GHLE in SBG Loop. |
|