27-11-2020
Press Release:REPORT ON DELAY IN COMMISSIONING OF MAJERHAT ROB • JOINT SAFETY CERTIFICATE RECEIVED BY RAILWAY ON 27.11.2020 FROM STATE AUTHORITIES



REPORT o­n DELAY IN COMMISSIONING OF MAJERHAT ROB
•JOINT SAFETY CERTIFICATE RECEIVED BY RAILWAY 
ON 27.11.2020 FROM STATE AUTHORITIES
Kolkata, November 27, 2020
 
            In some media, a news has appeared o­n 27.11.2020 describing as if Railway is responsible for the delay in opening of Majerhat Road Overbridge (ROB). Following points indicating up-do-date development/status of re-building of Majerhat ROB are placed hereunder for clear appreciation of the problem.
 
1)    Majerhat ROB collapsed in September, 2018 apparently due to maintenance failure. The structure was under the maintenance of PWD, Govt of WB. Initially the Government of West Bengal decided to rebuild the ROB with bow string steel girders, but in January 2019 they changed the decision to rebuild it as a cable stayed type ROB. It led to loss of time by more than four (4) months.
 
2)    Metro Railway Joka  - B B D Bag alignment is parallel to the proposed ROB at Majerhat. As per planning made by the engineers of the Government of West Bengal, north-end approach of the proposed ROB was infringing with the Metro Railway alignment. In spite of repeated requests by ER to get the nod of RVNL/Metro regarding infringement of proposed Majerhat ROB before finalizing the alignment of Majerhat ROB, it was delayed by PWD. The matter was at last resolved with the intervention of Chief Secretary of Government of West Bengal, which led to loss of time by more than o­ne & half months.
 
3)    The draft design & drawings of the super structure submitted by the PWD, Government of West Bengal to Railway had multiple (29 Nos.) technical shortcomings. Ultimately, in a meeting held o­n 4th & 5th July, 2019 by Railways with the foreign designers engaged by the Government of West Bengal and the engineers of PWD, the issue was finally resolved. The final design & drawings for the super structure of the ROB were submitted by the PWD to Railways after about o­ne month of the above meeting.
 
4)    In order to avoid delay, PWD engineers were requested to attend the office of Chief Bridge Engineer/Eastern Railway o­n 4.11.2019 to comply with the observations made in connection with erection and the launching scheme after a thorough scrutiny thereof. The concerned officials from the PWD finally complied with the observations o­n 22.11.2019. o­n 22.11.2019 itself all the drawings & designs have been taken back by the officials of the PWD from the Railway Office for submission of the final drawings as per extant practice for approval of Railway.

5)    State PWD o­n 27.11.2019 submitted 22 drawings o­n the launching scheme to Railway. After scrutiny by Railway, the number of drawings for the launching scheme was increased from 17 to 22. Railway has approved the designs and all 
these 22 drawings o­n 28.11.2019 and PWD was requested to take away the approved drawings for filling of Commissioner Railway Safety application etc.
 
6)    The Commissioner Railway Safety (CRS) application for erection & launching of girder was submitted by the state authority to DRM/Sealdah o­n 2.12.2019. DRM/Sealdah has filed the Commissioner Railway Safety (CRS) application for erection & launching of girders to Commissioner Railway Safety, Eastern Circle o­n 4.12.2019. Commissioner Railway Safety Eastern Circle’s approval was accorded o­n 28.2.2020 with some stipulations.
 
7)    The final drawings of the bearings were submitted by State Govt. to Railways o­n 26.08.2020 and were approved by this Railway o­n the same day.
 
8)    Joint Safety Certificate received from State Govt o­n 27.11.2020 and submitted to CRS EC o­n date after signature of Railway Authority. State Govt. Has also been informed in writing o­n date that all statutory formalities regarding the ROB involving this Railway have been completed and they are now at liberty to take further action for arranging its opening for public.
 
It may be appreciated that nothing was left pending with Eastern Railway and there was no delay o­n the part of the Railway. Eastern Railway is always keen to complete job in coordination with all the agencies associated with construction of Majerhat ROB including PWD, Govt of WB and has taken all steps for early completion of the work.




  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.