Press Release: BOINCHI – SHAKTIGARH THIRD LINE, A SUPER CRITICAL PROJECT COMPLETED SUCCESSFULLY BY ER

    3, कोयलाघाट स्ट्रीट, कोलकाता – 700001, 3, Koilaghat Street, Kolkata – 700001


BOINCHI – SHAKTIGARH THIRD LINE, A SUPER CRITICAL PROJECT COMPLETED SUCCESSFULLY BY ER


Kolkata, September 17, 2022



Rasulpur – Shaktigarh 3rd line work has been successfully completed by Eastern Railway in record time thereby accomplishing Boinchi – Shaktigarh 3rd line project, which is a super critical project. Completion of this project will improve mobility & speed of the entire Howrah – Bardhhaman stretch and line capacity over both Howrah – Bardhhaman main line as well chord line.


The commissioning of 3rd line has been successfully done after massive non-interlocking work which involved remodelling & electronic interlocking (EI) work of Shaktigarh yard which is a critical junction of Howrah – New Delhi Chord line & Main line. The difficult work involved cut & connect of all the three lines in block section due to typical layout. The herculean work of yard remodelling and cut & connect in the mid section including TRD and S&T works completed in 11 days' pre Non-interlocking (NI) & 48 hours' non-interlocking. The Electronic Interlocking (EI) was done at Shaktigarh for 154 routes and at Rasulpur for 76 routes. Major overhead wire (OHE) modification work was also involved in this work at Shaktigarh yard over seven (7) cross-overs and other 350 structures. For completing this mammoth work within the prescribed timeframe, 750 labourers, 17 supervisors, 150 overhead (OHE) wire workers & 6 officers were deployed continuously day & night.


Commissioner of Railway Safety inspected the last block section of the above project, i.e., Rasulpur – Shaktigarh (6.95 km) with detailed trolley inspection followed by speed trail. CRS was satisfied in the inspection & authorisation is expected shortly for commissioning of this mega third line project. 


Generally, work of such magnitude involving yard remodelling & introduction of new system of interlocking of signals requires several days’ restriction of train traffic movement. To avoid such inordinately lengthy traffic block, innovative planning was done for commissioning work thereby ensuring minimum most traffic disruption & less passenger inconvenience. Adept & dedicated workforce of Eastern Railway were able to complete the super critical project with minimum possible disturbance to normal train movement.


After commissioning of the all important 3rd line project, the movement of trains over Eastern Railway’s Howrah division (in both Main and Chord lines) will be eased up substantially resulting significant improvement in punctuality of mail/express & suburban trains. Moreover, it will enhance the average speed of mail/express/passenger/EMU & goods trains by virtue of which the suburban passengers will be greatly benefitted.






  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.